Oil & gasQatar · 2024 · €250K
Turboden S.p.A. — RCC
Prefabricated pipelines for a new power generation system at a cement plant in Qatar: DN25 to DN1000, 100 % NDT, every spool hydrotested.
Project data sheetRCC
- Client
- Turboden S.p.A.
- Sector
- Oil & gas
- Location
- Qatar
- Year
- 2024
- Contract value
- €250K
- Diameter range
- DN25 – DN1000
- Material
- On request
Project overview
Prefabrication of pipelines for a new power generation system at a cement manufacturing facility in Qatar. The scope included material sourcing, fabrication of pipe spools to isometric drawings and preparation for installation.
Challenges and execution
A broad range of pipe diameters (DN25–DN1000) demanded stringent quality control:
- Materials procured and prepared to precise technical standards
- Radiographic, penetrant and visual inspection of every weld
- Hydrostatic testing of every spool for operational integrity
- Sandblasting and a three-layer coating system to the technical specification
- Fabrication aligned with the installation schedule on site
Key deliverables
- Complete prefabricated pipe spools in multiple diameters
- 100 % NDT inspection (RT, PT, VT) and certification of all welds
- Hydrostatic testing confirming system reliability
- Surface treatment and coating in full compliance with the specifications
- Documentation for traceability and adherence to project standards
Outcome and impact
Fully certified, installation-ready pipelines that reduced assembly risk on site and support reliable operation of the power generation system. Streamlined fabrication and rigorous quality management kept the delivery on time and technically compliant.
This project demonstrates ML Weld Engineering’s technical capability and problem-solving: workshop capacity combined with expert engineering let the client execute a high-stakes project on time, to quality and with minimal risk.
More references
Comparable projects
Oil & gasTurboden — High-Pressure Pipeline Installation
Fabrication and installation of high-pressure pipelines from DN50 to DN1000 in Saudi Arabia, delivered in five months.
DN50 – DN1000
Data centreFRA13 — Chilled Water Pipeline Installation
Installation of 1,500 metres of chilled-water pipeline inside a data centre in Germany, with insulation and support systems.
Data centreFRA21 — Chilled Water Pipeline Prefabrication
Prefabrication of chilled-water systems for a data centre in Germany: 17,000 diameter-inches of carbon steel spools, blasted and painted in-house.
Request for quotation
Send us your piping package
Tell us the material, the diameter range, the quantity, the standards and where it has to be delivered. Our engineers reply with questions or a quotation.
Request a quote+381 69 515 64 18
Isometrics and drawings by e-mail: office@mlweld.rs