Data centreGermany · 2023/24 · €1.6M

FRA13 — Chilled Water Pipeline Installation

Installation of 1,500 metres of chilled-water pipeline inside a data centre in Germany, with insulation and support systems.

Project data sheetFRA13

Client
Not disclosed
Sector
Data centre
Location
Germany
Year
2023/24
Contract value
€1.6M
Duration
8 months
Diameter range
On request
Material
On request
Key figure
1,500 m of chilled-water pipeline
FRA13 — Chilled Water Pipeline Installation

Project overview

Installation of 1,500 metres of chilled-water pipeline within a data centre, including full assembly of the insulation and support systems. The project covered precision welding, joint alignment, on-site testing and integration into the existing infrastructure.

Challenges and execution

A long chilled-water run in a sensitive data-centre environment required meticulous planning and strict quality control:

  • Sequenced installation to minimise disruption to ongoing operations
  • Precision welding and alignment for hydraulic efficiency and pressure integrity
  • On-site pressure testing and inspection to verify system performance
  • Insulation and support assemblies integrated for thermal efficiency and structural stability

Key deliverables

  • A fully installed 1,500 m chilled-water pipeline
  • High-precision welding and joint alignment
  • Comprehensive pressure testing and quality verification
  • Complete insulation and support system installation
  • Documentation of all testing and compliance with engineering standards

Outcome and impact

A reliable, efficient chilled-water distribution system, installed with minimal operational downtime. Precise execution and thorough quality assurance secured long-term performance, flow efficiency and compliance with data-centre standards.

This project demonstrates ML Weld Engineering’s technical capability and problem-solving: workshop capacity combined with expert engineering let the client execute a high-stakes project on time, to quality and with minimal risk.

From the workshop and the site

Photographs

FRA13 — Chilled Water Pipeline Installation — photograph from the project
FRA13 — Chilled Water Pipeline Installation — photograph from the project
FRA13 — Chilled Water Pipeline Installation — photograph from the project
FRA13 — Chilled Water Pipeline Installation — photograph from the project

Request for quotation

Send us your piping package

Tell us the material, the diameter range, the quantity, the standards and where it has to be delivered. Our engineers reply with questions or a quotation.

Request a quote+381 69 515 64 18

Isometrics and drawings by e-mail: office@mlweld.rs