Data centreGermany · 2023/24 · €1.6M
FRA13 — Chilled Water Pipeline Installation
Installation of 1,500 metres of chilled-water pipeline inside a data centre in Germany, with insulation and support systems.
Project data sheetFRA13
- Client
- Not disclosed
- Sector
- Data centre
- Location
- Germany
- Year
- 2023/24
- Contract value
- €1.6M
- Duration
- 8 months
- Diameter range
- On request
- Material
- On request
- Key figure
- 1,500 m of chilled-water pipeline

Project overview
Installation of 1,500 metres of chilled-water pipeline within a data centre, including full assembly of the insulation and support systems. The project covered precision welding, joint alignment, on-site testing and integration into the existing infrastructure.
Challenges and execution
A long chilled-water run in a sensitive data-centre environment required meticulous planning and strict quality control:
- Sequenced installation to minimise disruption to ongoing operations
- Precision welding and alignment for hydraulic efficiency and pressure integrity
- On-site pressure testing and inspection to verify system performance
- Insulation and support assemblies integrated for thermal efficiency and structural stability
Key deliverables
- A fully installed 1,500 m chilled-water pipeline
- High-precision welding and joint alignment
- Comprehensive pressure testing and quality verification
- Complete insulation and support system installation
- Documentation of all testing and compliance with engineering standards
Outcome and impact
A reliable, efficient chilled-water distribution system, installed with minimal operational downtime. Precise execution and thorough quality assurance secured long-term performance, flow efficiency and compliance with data-centre standards.
This project demonstrates ML Weld Engineering’s technical capability and problem-solving: workshop capacity combined with expert engineering let the client execute a high-stakes project on time, to quality and with minimal risk.
More references
Comparable projects
Data centreFRA21 — Chilled Water Pipeline Prefabrication
Prefabrication of chilled-water systems for a data centre in Germany: 17,000 diameter-inches of carbon steel spools, blasted and painted in-house.
Data centreStainless Steel & Carbon Pipe Spools
Stainless and carbon double pipe spools for a large data-centre development in Belgium: engineering support, prefabrication, installation, documentation.
Data centreITA01 — Chilled Water Pipeline Systems
Fabrication and installation of chilled-water pipelines for a live data centre in Italy: corrosion-resistant modules and in-house pressure testing.
Request for quotation
Send us your piping package
Tell us the material, the diameter range, the quantity, the standards and where it has to be delivered. Our engineers reply with questions or a quotation.
Request a quote+381 69 515 64 18
Isometrics and drawings by e-mail: office@mlweld.rs